How to calculate concrete for a slab
Concrete is sold by volume, in cubic metres. A 4 m × 3 m pad that is 100 mm thick works out to 4 × 3 × 0.1 = 1.2 m³, and with 10% extra you would plan for about 1.32 m³.
The margin matters. Ground is rarely perfectly level, formwork bows a little, and some concrete always stays in the barrow or the chute. Running short halfway through a pour leaves a cold joint, which is far worse than having a little left over. For an L-shaped slab, split it into rectangles, work out each one and add them together.
How many bags of concrete do I need?
Divide the volume by what one bag makes. A 20 kg bag of general-purpose premix makes roughly 0.0095 m³, so one cubic metre takes about 105 bags before waste. A 30 kg bag makes roughly 0.014 m³, or about 72 bags per cubic metre. Yields vary between brands, so check the label on the bag you're buying.
| Volume | 20 kg bags | 30 kg bags |
|---|---|---|
| 0.1 m³ | 11 | 8 |
| 0.25 m³ | 27 | 18 |
| 0.5 m³ | 53 | 36 |
| 1 m³ | 106 | 72 |
Before waste. Add 5–10% on top, as the calculator does.
For fence and pergola posts, many people use a fast-setting post mix instead of standard premix. Some of these are designed to be poured dry into the hole and then wetted, so the number of bags per hole can differ: follow the instructions on the bag.
Footings, piers and post holes
A strip footing is a long, narrow slab, so the same formula applies: total length × width × depth. For round post holes, the calculator works out the volume of each cylinder (π × radius² × depth), takes away the space the post itself fills, and multiplies by the number of holes. For round concrete piers or pier footings with no post set in them, enter a post size of 0.
Dug holes and trenches usually end up wider than planned, which is why 10% extra is a sensible default for these jobs.
How thick should a concrete slab be?
| Job | Common thickness |
|---|---|
| Garden path, light foot traffic | 75–100 mm |
| Shed or water tank pad | 100 mm |
| Driveway for cars | 100–125 mm, reinforced |
| House slab or footings | Engineer-designed (AS 2870) |
Common starting points, not a design. Your council, the tank or shed manufacturer, or an engineer may require something different.
Bags, mini-mix or ready-mix?
The calculator's Bags–Truck bar shows where your job falls. As a rule of thumb:
Under 0.3 m³
Premix bags, mixed by hand or in a small mixer. Posts and small pads.0.3–0.6 m³
Either. Compare bag cost and effort with a mini-mix or a ready-mix short load.Over 0.6 m³
Ready-mix delivered by truck. Driveways and larger slabs.Mini-mix services use smaller trucks for small loads and tight access, which makes them a common choice for jobs too big for bags but too small for a full ready-mix truck. When you ask for quotes, give the supplier your volume in m³ from the calculator and ask whether a minimum load or short-load fee applies.
Working out the cost of your concrete
Concrete is priced per cubic metre delivered, and the price changes with your location, the strength you need (measured in MPa), the size of the load and how far the truck travels. Extras such as a concrete pump, colour or exposed-aggregate finishes, and short-load fees are added on top. The concrete price per m³ calculator estimates the delivered cost by city, and the concrete driveway cost calculator prices a whole driveway, labour included.
To estimate the material cost, get a delivered price per m³ from a couple of local suppliers and enter it in the Ready-mix price per m³ field above, or use our concrete price per m³ calculator for typical prices by city, short-load fees and pump hire. The calculator multiplies it by the rounded order volume. Labour, formwork, reinforcement and finishing are separate, so for a driveway or slab ask a concreter for a full quote.
Before you pour
- Measure the formwork you actually built, not the plan.
- Check access: can a truck reach the site, or will you need a pump or barrows?
- Avoid pouring in extreme heat or when rain is forecast, as both affect the finish and strength.
- Keep the slab damp for the first few days so it cures properly.
Frequently asked questions
How many 20 kg bags of concrete are in a cubic metre?
Roughly 100 to 110 bags, because a 20 kg bag of premix usually makes around 0.009–0.01 m³ once mixed. Yields vary by brand, so check the bag label and choose the matching bag size in the calculator.
How do I calculate how much concrete I need?
Multiply length × width × depth, all in metres, to get cubic metres (m³). For a 4 m × 3 m slab that is 100 mm thick: 4 × 3 × 0.1 = 1.2 m³. Then add 5–10% for waste, uneven ground and spillage.
How many bags of concrete do I need for a fence post?
For a typical 90 mm post in a 300 mm wide, 600 mm deep hole, each hole needs about 0.04 m³, which is roughly 4 to 5 bags of 20 kg premix including some waste. Use the Post holes option to work it out for your hole size and number of posts.
Should I use bags or order ready-mix concrete?
Bags suit small jobs such as setting posts or a small pad. Once a job needs more than about half a cubic metre, mixing by hand gets slow and tiring, and a ready-mix truck is usually easier and gives a more consistent pour. Ask local suppliers about minimum order sizes and short-load fees.
Can I mix concrete by hand?
Yes, for small jobs. A wheelbarrow or mixing tray and a shovel are enough for a few bags at a time. Beyond about a dozen bags it becomes slow, tiring and hard to keep the pour even, so hire a small mixer or order a mini-mix or ready-mix load instead.
How much does concrete cost per m³?
It depends on your city, the strength (MPa), the load size and the supplier, and small loads usually carry an extra short-load fee. Ask two or three local suppliers for a delivered price per m³, then enter it in the calculator to see your total.
How thick should a concrete slab be?
It depends on what the slab carries. Paths are often 75–100 mm, and driveways for cars are commonly 100–125 mm with reinforcement. Structural slabs for houses are designed by an engineer to AS 2870, so do not guess those.
How much extra concrete should I order?
Most people add 5–10%. Use the higher end if the ground is uneven, the formwork is irregular, or you are pouring footings into dug trenches, where the actual volume is often more than planned.
Results are estimates to help you plan and compare quotes. They are not a substitute for advice from a licensed tradesperson or engineer.